Changes not visible to others

We use Project 2016 at work.  I've created a Project plan on a SharePoint that is accessible to others. But we're continually having issues where someone will make a change then the other person goe...
  • RodFromm's avatar
    RodFromm
    Mar 20, 2024

    tori2024 - With project online only one user at a time can check out a project.  Whoever checks out the project, they must Publish their changes and check the project in before other can see the changes.  There is no work around.