Change working Days in Project for the Web
I have been exploring Project for the Web and came across a requirement of changing the working days around, as in Dubai weekends are usually Friday and Saturday therefore Sunday is considered the be...
RTTech2475
Aug 05, 2022Brass Contributor
Brian-Smith used the documentation linked, made a new calendar template and a resource that was 24/7/365 and still unable to schedule on the weekends.
Brian-Smith
Aug 06, 2022Former Employee
You best get your admin to open a support ticket and we can look deeper. I assume you added the calendar after setting the working time in the template? When you assign a calendar it actually makes a copy of the template - and any further changes to the template do not make it to the plan unless the calendar is removed and a new copy assigned.