Forum Discussion
oharbe
Jun 20, 2020Copper Contributor
Change working Days in Project for the Web
I have been exploring Project for the Web and came across a requirement of changing the working days around, as in Dubai weekends are usually Friday and Saturday therefore Sunday is considered the be...
Brian-Smith
Jun 24, 2020Former Employee
oharbe this article should help with your need to change the calendar https://docs.microsoft.com/en-us/project-for-the-web/create-and-apply-a-work-calendar Let me know if you have further questions.
Best regards,
Brian
RTTech2475
Aug 05, 2022Brass Contributor
Brian-Smith used the documentation linked, made a new calendar template and a resource that was 24/7/365 and still unable to schedule on the weekends.
- Brian-SmithAug 06, 2022Former EmployeeYou best get your admin to open a support ticket and we can look deeper. I assume you added the calendar after setting the working time in the template? When you assign a calendar it actually makes a copy of the template - and any further changes to the template do not make it to the plan unless the calendar is removed and a new copy assigned.