change time recording from weekly to daily in project online
Hi Our company has just changed the timesheet capture from weekly to daily, and now the timesheet report in PowerBI doesn't work. It says there is duplicate data in an Assignment field. Any ideas?
- Jul 09, 2020
Hi Sue Adirondacks ,
Try changing the relationship for one to many - one from TimesheetLines to many TimesheetLineActuals
Paul
Adirondacks
Jul 09, 2020Copper Contributor
Paul_Mather
Jul 09, 2020MVP
Hi Sue Adirondacks ,
Try changing the relationship for one to many - one from TimesheetLines to many TimesheetLineActuals
Paul