Change Print Page Order
Hello, I'm looking to see if someone can help me find how to change the order that pages are printed in Project. Personally, I know this doesn't matter because you can just line them up as you like, ...
PlannersPlace
Nov 17, 2025Brass Contributor
Have you tried changing the Gantt Chart Timescale?
Try changing the Middle Tier to Years and the Bottom Tier to Months. And ensure that the size is 100% or below. Keep adjusting until the Gantt Chart timeline is a page wide.
Alternatively, in Print Preview, use Page Setup to change the Scaling. Either adjust to below 100% or fit to 1 page wide.