Forum Discussion
Cashflow Visual report export
- Nov 21, 2025
PageAndSquire,
It sounds like you want a cash flow for accounting months used by your company. Unfortunately that isn't an easy ask as Project has no functionality for producing output in anything other than calendars periods.
For Visual Reports you won't be able to display weekly dates so you have to do some interpretation to get the accounting month periods you want. It gets a little better if you export days but that's a much larger pivot table and you still need to interpret start and end days for each period.
When faced with the need to report Project data in accounting months I use VBA.
Not the answer you wanted, but it's a basic limitation Project has had since day 1.
This could be using Power Query in Excel, much easier than VBA, but I'd have to sample data to give you more details.