Forum Discussion

Jamie Salbeck's avatar
Jamie Salbeck
Copper Contributor
Jun 08, 2023

Capture Actual Date Task Was Checked Off

Is there any way to capture when a task was actually checked off using either a custom formula or maybe some fields I am not aware of? Or what about Finish Variance? Is there a way to use that field to see the difference between when a tasked was checked off vs Finish Date? Thanks for any help or suggestions!

7 Replies

  • John-project's avatar
    John-project
    Silver Contributor
    Jamie Salbeck,
    Is there a way? Yes, but it would require using an event based macro to capture the current date based on the task being marked as complete. The same with the Finish Date or Variance.
    John

Resources