Capacity Planning issue

Hi, I am facing an issue when trying to change the Capacity Planning date range. When I try to select the date range it the Capacity Planning, it is throwing me an error (shown below). I have set t...
  • AmitWairkar1's avatar
    AmitWairkar1
    Jan 06, 2022

    DavidGarcez 

     

    I had logged a call with Microsoft. The below steps helped me resolve the issue:

     

    1. PWA Change the capacity planning ahead of 6 months and 4 months before.
    2. Go to the production APP site setting -> Site collection features
    3. Disable the Project webapp and setting site collection feature of the PWA and then again enable it
    4. Ran the following command to check the provisioning state of the PWA get-spprojectwebinstances
    5. The main PWA provisioning state should be online now.
    6. After That run the project resource planning sync timer job by going to the Central Admin->Monitoring->Job definition
    7. Check the  resource planning sync job in PWA queue job ,
    8. Cancel all the failed and blocked jobs.
    9. Then wait for some time to let this resource planning sync job to success.