Forum Discussion
Capacity Planning issue
- Jan 06, 2022
I had logged a call with Microsoft. The below steps helped me resolve the issue:
- PWA Change the capacity planning ahead of 6 months and 4 months before.
- Go to the production APP site setting -> Site collection features
- Disable the Project webapp and setting site collection feature of the PWA and then again enable it
- Ran the following command to check the provisioning state of the PWA get-spprojectwebinstances
- The main PWA provisioning state should be online now.
- After That run the project resource planning sync timer job by going to the Central Admin->Monitoring->Job definition
- Check the resource planning sync job in PWA queue job ,
- Cancel all the failed and blocked jobs.
- Then wait for some time to let this resource planning sync job to success.
Hello AmitWairkar1 ,
The job will run on a schedule once a day - check tomorrow if you changed the setting today.
Paul
- AmitWairkar1Jun 15, 2021Copper Contributor
Paul - I had changed the settings yesterday and the overnight run went successfully, but still it is showing capacity till 30th April'21. I tried it on the test server and prod server both. But yet it is showing the same date.
I have also attached the message that I am receiving in Capacity Planning for a resource and the settings that I have done in the Resource Capacity Settings.
- DavidGarcezJan 06, 2022Copper Contributor
AmitWairkar1 i have the same problem.
One of my users is trying to use the Capacity Planning and he get's the same message.
I am the administrator and i've configured it for over a week on PWA Aditional Server Settings with 12 months behind and another 12 months ahead... but the problem persists.
Really don't know what else to do.
Could someone please help?- AmitWairkar1Jan 06, 2022Copper Contributor
I had logged a call with Microsoft. The below steps helped me resolve the issue:
- PWA Change the capacity planning ahead of 6 months and 4 months before.
- Go to the production APP site setting -> Site collection features
- Disable the Project webapp and setting site collection feature of the PWA and then again enable it
- Ran the following command to check the provisioning state of the PWA get-spprojectwebinstances
- The main PWA provisioning state should be online now.
- After That run the project resource planning sync timer job by going to the Central Admin->Monitoring->Job definition
- Check the resource planning sync job in PWA queue job ,
- Cancel all the failed and blocked jobs.
- Then wait for some time to let this resource planning sync job to success.