Capacity Planning issue
Hi, I am facing an issue when trying to change the Capacity Planning date range. When I try to select the date range it the Capacity Planning, it is throwing me an error (shown below). I have set t...
- Jan 06, 2022
I had logged a call with Microsoft. The below steps helped me resolve the issue:
- PWA Change the capacity planning ahead of 6 months and 4 months before.
- Go to the production APP site setting -> Site collection features
- Disable the Project webapp and setting site collection feature of the PWA and then again enable it
- Ran the following command to check the provisioning state of the PWA get-spprojectwebinstances
- The main PWA provisioning state should be online now.
- After That run the project resource planning sync timer job by going to the Central Admin->Monitoring->Job definition
- Check the resource planning sync job in PWA queue job ,
- Cancel all the failed and blocked jobs.
- Then wait for some time to let this resource planning sync job to success.
Jun 15, 2021
Amit -- You forgot to include the screenshot of the error. It would help if we knew what error you are seeing. Please update and let us know.
AmitWairkar1
Jun 15, 2021Copper Contributor
Dale_HowardMVP I am not receiving any error as such. I am able to save all settings but the data is not getting updated.