Forum Discussion
AmitWairkar1
Jun 15, 2021Copper Contributor
Capacity Planning issue
Hi, I am facing an issue when trying to change the Capacity Planning date range. When I try to select the date range it the Capacity Planning, it is throwing me an error (shown below). I have set t...
- Jan 06, 2022
I had logged a call with Microsoft. The below steps helped me resolve the issue:
- PWA Change the capacity planning ahead of 6 months and 4 months before.
- Go to the production APP site setting -> Site collection features
- Disable the Project webapp and setting site collection feature of the PWA and then again enable it
- Ran the following command to check the provisioning state of the PWA get-spprojectwebinstances
- The main PWA provisioning state should be online now.
- After That run the project resource planning sync timer job by going to the Central Admin->Monitoring->Job definition
- Check the resource planning sync job in PWA queue job ,
- Cancel all the failed and blocked jobs.
- Then wait for some time to let this resource planning sync job to success.
Jun 15, 2021
Amit -- You forgot to include the screenshot of the error. It would help if we knew what error you are seeing. Please update and let us know.
- AmitWairkar1Jun 15, 2021Copper Contributor
Dale_HowardMVP I am not receiving any error as such. I am able to save all settings but the data is not getting updated.