Can't See the Detail and Tracking Gantt Charts
Hello to everybody,
I am using MS Project Professional version and I am currently facing some issues with displaying the Gantt chart bars on the right side of the screen when using the Detail Gantt and Tracking Gantt. In other words, I can only see the left side of the screen with all the associated tasks included, but not the corresponding charts themselves.
Does anybody have a clue why is this happening? Is it maybe a view setting that I need to adapt?
Thank you in advance!
Asimina.
Hello,
If you hover over the far right next to the scrollbar you should be able to grab the view splitter bar and move it left to reveal the Gantt?
Paul
4 Replies
Hello,
If you hover over the far right next to the scrollbar you should be able to grab the view splitter bar and move it left to reveal the Gantt?
Paul