Can't see activities assigned.

My resources can't see their activities assigned by me on Project Web App. I checked all the permissions that they have and they are Admins. 

4 Replies

  • Hello OscarVerdin ,

    Who is the Assignment Owner for these assignments? Does the Assignment Owner value match the Resource Names you are assigning to the Tasks?

    Paul

    • OscarVerdin's avatar
      OscarVerdin
      Copper Contributor

      Hello Paul_Mather 

       

      I'm the owner of the project, first I made the project on Project Pro before to save the project I published it on my PWA site and automatically it's saved on my PC. when I assigned resources, I selected them from the "Creat team company" and they recived the notification on their email. Yes, the Assignment Owner value match the resource names.

       

       

      Thank you Paul! 

       

      - Oscar.

      • Paul_Mather's avatar
        Paul_Mather
        MVP

        Hi OscarVerdin ,

        Is that screen shot for a new blank project? So when the users go to PWA Tasks {PWA site}/Tasks.aspx they see an empty grid? Any filters applied?