Can't reduce row height - tried everything!
Hi there, I have a master plan which brings together a number of subprojects. I want to display just the summary tasks of each subproject to show the phasing of our entire portfolio. Even though row...
John-project
Sep 19, 2025Silver Contributor
Naomi,
Can you show a screen shot? I don't quite understand about the white space between rows.
John
- NaomiBrillSep 19, 2025Brass Contributor
Hi John,
Thanks for your response.
See attached - I'd like to reduce the row height so there is less space between bars; so the gantt is more compact.
Cheers,
Naomi
- John-projectSep 19, 2025Silver Contributor
Naomi,
Not exactly the screen shot I was expecting (i.e. it doesn't show the actual Gantt Chart view), but let's check a few things.
- Are you using the default Calibri font or another font? Some fonts cause issues with row heights.
- In your initial post you said the row height was set to 1. Do you really mean the bar height (Gantt Chart Format > Format group > Layout > Bar Height)?
- Go to, Gantt Chart Format > Bar styles group > Format > Bar Styles. In the Bar Styles sub-window is the Row column set to 1 for all entries?
John
- NaomiBrillSep 19, 2025Brass Contributor
Sorry is this a better image?
Font is Calibri.
Rows are all set to 1 in bar styles.
Bar height was 12 but I've changed it to 6 (lowest option available) however nothing seems to have changed when I did this