Cannot edit page even with the administrator account.

Hello! I don't know if this is a usual problem but, from the last three months i can't edit the main sharepoint page for PWA. When I try to click on "edit page" the pages just "blink" and nothing happens... have you ever heard about something like that?

 

Thanks a lot.

 

Ps. I'm an Adm account with full control.

  • GSBERNARDES This issue was caused by a changed Microsoft implemented to remove custom scripting from OneDrive and SharePoint.  You will need your Global SharePoint Admin to go M365 Message Central and review Message ID MC714186. Basically, they will need to run a PowerShell script to re-enable custom scripting on affected PWAs, which will enable custom scripting for 24 hours.  Your admin will need to run this script daily or schedule a job to run the script to enable custom scripting.

1 Reply

  • RodFromm's avatar
    RodFromm
    Steel Contributor

    GSBERNARDES This issue was caused by a changed Microsoft implemented to remove custom scripting from OneDrive and SharePoint.  You will need your Global SharePoint Admin to go M365 Message Central and review Message ID MC714186. Basically, they will need to run a PowerShell script to re-enable custom scripting on affected PWAs, which will enable custom scripting for 24 hours.  Your admin will need to run this script daily or schedule a job to run the script to enable custom scripting.