Forum Discussion
Cannot connect to PWA
- Aug 26, 2021
allyally123 --
When you launch Microsoft Project, do you see a Login dialog? If not, click File > Info > Manage Accounts and then select the Configure Accounts item. In the lower left corner of the Project Web App Accounts dialog, select the Choose An Account item, and then click the OK button. Exit Microsoft Project and then re-launch the software. In the Login dialog, click the Profile pick list and select the correct login account for your organization's Project Online system, and then click the OK button. Please let us know if this helps.
allyally123 --
When you launch Microsoft Project, do you see a Login dialog? If not, click File > Info > Manage Accounts and then select the Configure Accounts item. In the lower left corner of the Project Web App Accounts dialog, select the Choose An Account item, and then click the OK button. Exit Microsoft Project and then re-launch the software. In the Login dialog, click the Profile pick list and select the correct login account for your organization's Project Online system, and then click the OK button. Please let us know if this helps.