Cannot assign resources to project tasks in Project Server 2019

Hi, I just installed an out-of-the-box Project Server on Sharepoint 2019 and modified the PWA to use project permissions. I added the resources from the AD sync method and the resources are now acti...
  • Dale_HowardMVP's avatar
    Oct 02, 2023
    noorulahmed --

    Did you build a team for the project using enterprise resources? That is the first step before you can assign resources to tasks. Also, I would strong recommend that you manage your projects using the Project Online Professional app (aka Microsoft Project desktop app) which will need to be connected to your Project Server instance. Using the desktop app to manage your projects will give you way more functionality and way more control over your projects. Just a thought. Hope this helps.