Forum Discussion

Vasily_Zaytsev's avatar
Vasily_Zaytsev
Iron Contributor
Jul 15, 2022
Solved

Can we unassign enterprise resource from AD user account?

Hello. Can we unassign enterprise resource from AD user account? The main goal of this - user can't be assign to any enterprise project.
  • Dale_HowardMVP's avatar
    Jul 15, 2022
    Vasily -- To prevent the resource from being assigned to any enterprise projects, why don't you just set the resource to Inactive status? That would make the user disappear from the Build Team dialog for all of your project managers. Just a thought. Hope this helps.