Can a Task Custom Field formula refer to a different task?

Hello, I suspect the answer is no but I thought I would post anyway in case someone smarter than me says it will work 🙂 I was wondering if it was possible for a formula in a Task Custom Field to r...
  • Dale_HowardMVP's avatar
    Feb 10, 2022
    Gilgamesh1964 - As you expected, the answer is no. You cannot write a formula that refers to a different task. Sorry, but hope this helps.