Calulated date is incorrect
My Microsoft Project isn’t working correctly. See line 25 should start 7 days after line 6’s completion date since I have everything marked as auto Schedule. see photo below
Jumpstart Admin not 6SF+7, Please 6FS+7. have a nice day
1 Reply
- ineejuTin Contributor
Jumpstart Admin not 6SF+7, Please 6FS+7. have a nice day