Forum Discussion

sirsleep29's avatar
sirsleep29
Brass Contributor
Dec 28, 2023

Calendars

I have a schedule that I have been working on for about 9 months now which is built on the standard 5 day work week. Now, I want to possibly change the current schedule to a 7 day work week. How hard...
  • Ignacio_Martin's avatar
    Ignacio_Martin
    Jan 25, 2024
    Hi.
    The first thing is to make a backup copy of the file, in case you don't like the results, but not because errors are generated.
    Keep in mind that the calendar will only be applied to unfinished tasks, and only from the date on which you define the application of the new calendar hours.
    Regards.
    Ignacio

Resources