Forum Discussion
sirsleep29
Dec 28, 2023Brass Contributor
Calendars
I have a schedule that I have been working on for about 9 months now which is built on the standard 5 day work week. Now, I want to possibly change the current schedule to a 7 day work week. How hard...
- Jan 25, 2024Hi.
The first thing is to make a backup copy of the file, in case you don't like the results, but not because errors are generated.
Keep in mind that the calendar will only be applied to unfinished tasks, and only from the date on which you define the application of the new calendar hours.
Regards.
Ignacio
sirsleep29
Jan 24, 2024Brass Contributor
Ignacio_Martin I think this will work for me but do you foresee any issues that could be caused by making the change? I worry that if I make the change and then all of a sudden I get a bunch of errors because of the change to the 7 day work week. Thank You.
Ignacio_Martin
Jan 25, 2024Steel Contributor
Hi.
The first thing is to make a backup copy of the file, in case you don't like the results, but not because errors are generated.
Keep in mind that the calendar will only be applied to unfinished tasks, and only from the date on which you define the application of the new calendar hours.
Regards.
Ignacio
The first thing is to make a backup copy of the file, in case you don't like the results, but not because errors are generated.
Keep in mind that the calendar will only be applied to unfinished tasks, and only from the date on which you define the application of the new calendar hours.
Regards.
Ignacio
- sirsleep29Jan 26, 2024Brass Contributorthank you Ignacio. You have been a big help. I am going to work on this today. My data has always been right in regard to start and finish tasks but the durations are incorrect and want to fix this.