Forum Discussion
sirsleep29
Dec 28, 2023Brass Contributor
Calendars
I have a schedule that I have been working on for about 9 months now which is built on the standard 5 day work week. Now, I want to possibly change the current schedule to a 7 day work week. How hard...
- Jan 25, 2024Hi.
The first thing is to make a backup copy of the file, in case you don't like the results, but not because errors are generated.
Keep in mind that the calendar will only be applied to unfinished tasks, and only from the date on which you define the application of the new calendar hours.
Regards.
Ignacio
Ignacio_Martin
Jan 02, 2024Steel Contributor
Happy New Year to all!
sirsleep29 , perhaps defining different workday periods in the project calendar could help you.
To achieve this, simply enter the project calendar and add a row "7 day work week" for example, and have it start at the beginning of that period and end on a date after the end of the project.
Next, click on Details of that same calendar period, and select all the days of the week, assigning the corresponding time, as shown in the image.
Nota.- The [Default] work week specifies the work week to be used when no other work week entry applies.
Ignacio
sirsleep29
Jan 03, 2024Brass Contributor
Good Morning, I appreciate the feedback and will try it out to see if it work for me. Thank You Again.