Forum Discussion

IngHartmann's avatar
IngHartmann
Copper Contributor
Jan 17, 2023

Calendar without specific months

Hello Team,

we want to create a calendar without specific months and holidays, because we are in planning now the flow but we don’t know exactly when the work will start concretely.

So, we want to create a calendar with “Week 1”, “Week 2” and so on. Every week should have the 5 working days and Saturday and Sunday.

Is it possible and someone can explain us how to do?

 

Best regards

Daniel

1 Reply

  • PlannersPlace's avatar
    PlannersPlace
    Brass Contributor

    IngHartmann

     

    Don't think you need a different calendar. Change your Gantt Chart timeline to ordinal dates and use Custom Number Fields to display Start & Finish Weeks in place of real dates. 

     

    This blog post from 2015 is for Project 2010 but should still work for you. https://www.plannersplace.com/blog/show-calendar-days-instead-of-dates-in-ms-project-schedule-columns