Calculation to show over allocation for a project in POL...
Hi team Does anyone have a formula I can use in POL to show if a resource is over-allocated in a project. It doesn't matter if other resources are under-allocated. Many thanks James
- Mar 27, 2023
Hi James_Price ,
I'm not sure this will be possible with an Enterprise Custom field in Project Online. The best option for this is in a report in either Excel or Power BI.
Paul
Paul_Mather
Mar 27, 2023MVP
Hi James_Price ,
I'm not sure this will be possible with an Enterprise Custom field in Project Online. The best option for this is in a report in either Excel or Power BI.
Paul
James_Price
Mar 29, 2023Brass Contributor
Thanks Paul. Unfortunately I thought this might be the case. Cheers