Forum Discussion
calculating how far behind a task is
Miles_Goodchild -- I would recommend you approach your project status question a little differently. Setting the Status date is good, and it should always represent the last day of the last reporting period. For many of us, the Status date is last Friday, Saturday, or Sunday.
After setting the Status date, manually enter task progress using whatever method or process that you prefer. For example, there was a task last week with a Duration of 5 days, starting on Monday and finishing on Friday, with a team member assigned to work full-time on the task. The team member should have finished last week, but he reporting that he is only 50% complete. You enter 50% in the % Complete column.
After entering task progress, you should RESCHEDULE incomplete work from the past into the current reporting period. In the case of the example task, there are 2.5 days of incomplete work that are still scheduled in last week. After rescheduling this incomplete work from last week into the current week, the Finish date of the task has now slipped 2.5 days.
To determine project and task slippage, apply the Tracking Gantt view to see the slippage visually. This assumes you saved a Baseline, however. You ARE saving a Baseline for each of your projects. Right? To see how many days of slippage you have in your project, apply the Variance table. In this table, you will see 2.5 days in the Finish Variance column for the task in question. If the task is a Predecessor, all Successor tasks will also show 2.5 days of Start Variance and Finish Variance. If the task is on the Critical Path, the Summary Summary Task (Row 0 or Task 0) will also show 2.5 days in the Finish Variance column.
So, to summarize, I would recommend you follow the process above, and focus your efforts on whether the project is running late, and if so, how late. Hope this helps.
- Miles_GoodchildJan 08, 2021Brass Contributor
Dale_HowardMVP Thank you for the suggestion which is a powerful approach which can be very useful. One weakness that this has is that if the team feels that despite the progress to date they can pull the time back and protect the end date this method doesn't allow for this. Obviously this doesn't apply in the example you gave; rather the team member would need to give a new finish date 🙂
Your comment on Baselines raises a smile 🙂
I have a nasty feeling that project will not be able to perform the calculation I want however I am hoping that someone can prove this incorrect.
Thanks
Miles
- John-projectJan 09, 2021Silver Contributor
If I may "dip my toe in the water". First understand that I am NOT a "whole lot smarter" than Dale with respect to Project, matter-of-fact, I'm not even close. However, what you want to do with Project reminds me of Alice's restaurant (i.e. "you can get anything you want"). Thanks to VBA, you can get virtually anything you want but, that doesn't mean the result will always be meaningful.
You mentioned in your original post that you'd like to have a metric comparing the current expected progress and actual percent complete (calculate what your eyes can see) and questioned whether "complete through" represented the current expected progress. For a non-summary task the "complete through" is simply duration multiplied by the entered percent complete value. For summary lines the relationship is a little more involved (basically a weighted average). So no, "complete through" is not expected progress.
Keep in mind that percent complete is a highly subjective metric. It is based on duration and actual duration and nothing is accomplished by the passage of time (i.e. duration) other than curing concrete or paint drying, etc. Actual progress should be based on effort (actual work) compared to estimated work for the task.
As Dale noted, the whole concept of expected versus actual is embodied in classic earned value metrics, although I've always taken exception to the concept of schedule variance based on cost. Aside from available earned value, what is the user's definition of "expected progress"?
If, as Dale suggested, the Tracking Gantt does not quite give what you want visually to "tweak the troops" into action, exactly what metric and visual display would work better? As I noted, anything can be coded with VBA, but will it mean anything?
My thoughts.
- Jan 10, 2021
John-project -- Nice comments, John. Thanks for sharing. 🙂
- Jan 08, 2021
Miles_Goodchild -- There is no direct method in Microsoft Project to compare the expected % complete progress with the actual % complete progress. The only way to do that is to use the EVA tables in the software. However, I doubt your team would find the EVA information to be of any value to them.
Unless someone a whole lot smarter than me knows how to create the formula you seek, then I think you might want to reconsider the advice I gave in my previous post. Sorry, but hope this helps.