Bulk export project .MPP file from Microsoft project
Hello Everyone, I am looking for a way to export project .mpp file in bulk for more than 100 projects form Microsoft project. Please suggest f there is any way to perform this task. Thanks in advan...
Paul_Mather
Sep 11, 2023MVP
Hello Shraddha_Sawant2210 ,
You could use VBA to do this. You'll find some examples online as I've seen various before such as: https://azlav.wordpress.com/2012/12/11/exporting-mpp-files-with-vba/
You might need to update this example if it doesn't work as it is quite old but it will give you the idea.
Paul