Forum Discussion
Kdekruif
Sep 22, 2023Copper Contributor
Bulk Edit Not Working
I would like to bulk edit tasks, specifically the Task Calendar. I highlight multiple rows (2 or more), select Information -> Advanced -> Calendar and then pick a calendar, but no changes are ma...
- Sep 27, 2023All --
I have the same version of Microsoft Project that others are using. I just did an extensive test on the features in the Multiple Task Information dialog, and can confirm that NOTHING is working in this dialog. I tried changing the Duration for a block of tasks. No go. I tried changing the constraint type to As Soon as Possible to a block of tasks, each of which has a SNET constraint applied, and no go again. It is obvious that Microsoft has introduced a bug into Microsoft Project, and this bug NEEDS TO BE FIXED. I will report this bug to my contacts within Microsoft to see if they can get the fix moving. Thanks so much to all for reporting this.
John-project
Nov 10, 2023Silver Contributor
Sandra_Kienitz,
Understood. A fix has not yet been released. I suggest you use the workaround I cited in my response on Sept 25 until the fix is released.
John
Understood. A fix has not yet been released. I suggest you use the workaround I cited in my response on Sept 25 until the fix is released.
John
rbuzeta
Nov 21, 2023Copper Contributor
According to new information received from Microsoft support staff, it is estimated that the solution to this BUG could be deployed on December 12, 2023
- Kelvin_KirbyDec 13, 2023Iron ContributorOh look - its Dec 13th & still no fix! 😞
- John-projectNov 21, 2023Silver Contributorrbuzeta,
I guess the "new information" is the Microsoft support staff finally admitting it is really a bug 🙂
John