Forum Discussion
Kdekruif
Sep 22, 2023Copper Contributor
Bulk Edit Not Working
I would like to bulk edit tasks, specifically the Task Calendar. I highlight multiple rows (2 or more), select Information -> Advanced -> Calendar and then pick a calendar, but no changes are ma...
- Sep 27, 2023All --
I have the same version of Microsoft Project that others are using. I just did an extensive test on the features in the Multiple Task Information dialog, and can confirm that NOTHING is working in this dialog. I tried changing the Duration for a block of tasks. No go. I tried changing the constraint type to As Soon as Possible to a block of tasks, each of which has a SNET constraint applied, and no go again. It is obvious that Microsoft has introduced a bug into Microsoft Project, and this bug NEEDS TO BE FIXED. I will report this bug to my contacts within Microsoft to see if they can get the fix moving. Thanks so much to all for reporting this.
John-project
Oct 11, 2023Silver Contributor
Solution? Yes, follow the procedure I outlined in my response on 25 September (above). As far as trying to use bulk editing via Task Information, I'm afraid you'll have to wait for a future update. The issue has been highlighted to Microsoft.
John
pfaria23
Oct 11, 2023Copper Contributor
Thanks for the quick reply, John! It worked 🙂
If I may, I will just include another step in case someone else is trying to bulk edit the Task Calendars. The fill down will not work if you try to copy the calendar by selecting the
"Indicator" column. You need to add the column "Task Calendar" and follow the procedure John mentioned.
If I may, I will just include another step in case someone else is trying to bulk edit the Task Calendars. The fill down will not work if you try to copy the calendar by selecting the
"Indicator" column. You need to add the column "Task Calendar" and follow the procedure John mentioned.
- John-projectOct 11, 2023Silver Contributorpfaria23,
Of course it works, it's the only method I've ever used 🙂
I thought the process was pretty obvious (i.e. a field can only be selected if it is displayed in the view) but your added step makes it more clear.
John