Both Reverse and Forward Planning in Projects
I have classes that I am loading into Projects. I set up the project to use "Schedule From Finish Date" so that I can enter the class date and then Projects tells me when I have to start setting up ...
RKN2021
Apr 16, 2021Copper Contributor
Hi Dale,
Thank you for your response! I have some questions:
1. I am unsure of the steps to follow in your #2 above. Do you mean to go to Project --> Project Information-->Schedule from: "Project Finish Date"?
2. Your step #3 would then be to go to Project -->Project Information-->Schedule from: "Project Start Date"?
Thanks,
RKN2021
Thank you for your response! I have some questions:
1. I am unsure of the steps to follow in your #2 above. Do you mean to go to Project --> Project Information-->Schedule from: "Project Finish Date"?
2. Your step #3 would then be to go to Project -->Project Information-->Schedule from: "Project Start Date"?
Thanks,
RKN2021
Apr 16, 2021
Yes, that is correct. But you need to apply the MSO constraint on the task representing the start date of the class before you do steps #2 and #3.