Both Reverse and Forward Planning in Projects
I have classes that I am loading into Projects. I set up the project to use "Schedule From Finish Date" so that I can enter the class date and then Projects tells me when I have to start setting up ...
RKN2021 -- I have had clients in the past who have needed this functionality. Here is how I recommend you do it:
1. On the task that represents the class, apply a Must Start On constraint and set the constraint date to the date that the class will start. This will "lock" the Start date of the task.
2. Set Microsoft Project to schedule backwards in time. This will calculate the date that the project needs to start.
3. Set Microsoft Project to schedule forwards in time. This will calculate the date that the project will finish.
4. Leave the scheduling mode set to schedule forwards in time.
Hope this helps.
1. On the task that represents the class, apply a Must Start On constraint and set the constraint date to the date that the class will start. This will "lock" the Start date of the task.
2. Set Microsoft Project to schedule backwards in time. This will calculate the date that the project needs to start.
3. Set Microsoft Project to schedule forwards in time. This will calculate the date that the project will finish.
4. Leave the scheduling mode set to schedule forwards in time.
Hope this helps.
RKN2021
Apr 16, 2021Copper Contributor
Hi Dale,
Thank you for your response! I have some questions:
1. I am unsure of the steps to follow in your #2 above. Do you mean to go to Project --> Project Information-->Schedule from: "Project Finish Date"?
2. Your step #3 would then be to go to Project -->Project Information-->Schedule from: "Project Start Date"?
Thanks,
RKN2021
Thank you for your response! I have some questions:
1. I am unsure of the steps to follow in your #2 above. Do you mean to go to Project --> Project Information-->Schedule from: "Project Finish Date"?
2. Your step #3 would then be to go to Project -->Project Information-->Schedule from: "Project Start Date"?
Thanks,
RKN2021
- Apr 16, 2021Yes, that is correct. But you need to apply the MSO constraint on the task representing the start date of the class before you do steps #2 and #3.