Forum Discussion

AndyGagnon's avatar
AndyGagnon
Copper Contributor
Jun 25, 2021
Solved

Best practices for adding planned slack to a project

Hi All!     my first post of many to come!   I'm interested in hearing any best practices of how to add planned slack to a project.  I manage a portfolio of about 300 mini-projects for a manufact...
  • TomBoyle's avatar
    Jun 27, 2021

    AndyGagnon, what you describe is not too far from accepted best practice, as long as you avoid the term "planned slack" (which implies a completely different concept.)  Conventional schedule risk management would suggest that appropriate terms like "schedule contingency", "schedule buffer", or "time risk allowance" can be added to a baseline schedule as long as they a) are based on a quantitative schedule risk analysis; and b) are allocated to schedule tasks in a way that reflects the true schedule risks.  Ideally, the forecast dates in such a risk-adjusted schedule should reflect a 50% chance of overrun/underrun.  Real-life project sponsors and customers typically demand a much higher probability of underrun, e.g. "promised" or "guaranteed" dates.  Unfortunately, such guarantees typically drive over-conservative buffers/contingencies and reduce the overall project value.

Resources