Forum Discussion

ghiasi-amir's avatar
ghiasi-amir
Copper Contributor
May 23, 2021
Solved

Bcwp problem in microsoft project

In the microsoft project 2019 program in the BCWP column, when considering the high amount for COST ($ 100,000,000,000) and then getting BASELINE, changing the Physical% complete values ​​from 10 to ...
  • Dale_HowardMVP's avatar
    Dale_HowardMVP
    May 24, 2021
    ghiasiamir -- I ran extensive tests on a task that has such a large Cost value and I can confirm exactly what you are experiencing, as I experienced it as well. This is obviously a bug in the software. I would recommend that you contact Microsoft Support and log this as a bug with them so that they can get it fixed. Until it is fixed, I do not have any workaround. Hope this helps.

Resources