Basic Admin Permissions

Hi   We have some PMO Administrators who we need to carry out some central administrative duties in Project Server, but do not want them to have full Admin permissions.   Can someone advise me of...
  • Dale_HowardMVP's avatar
    Jan 18, 2022
    APS1979 --

    The simplest way to handle this is to add these users to the default Portfolio Managers group. In Project Online and Project Server, a Portfolio Manager is a project manager with limited Administrator capabilities. After adding these users on the Add or Edit Group page for the Portfolio Managers group, select the My Organization item in the Selected Categories list. In the Permissions for My Organization data grid, select the Allow checkbox for the Save Protected Baseline permission. Click the Save button when finished and you are in business! Hope this helps.