Forum Discussion
kristi_in_heels
Jan 09, 2026Copper Contributor
Baseline Resourcing Assistance
Hello, I have been transferring a 1700 line schedule from a different program into MS Project. I have got the current schedule loaded and resourced, and all is working well. I have set this ...
Ignacio_Martin
Jan 10, 2026Iron Contributor
Hello Kristi_in_heels
Project doesn't calculate or relate the baseline data itself. Even if you enter the Start and Finish dates for the baseline, the Baseline Duration isn't calculated, nor is the Work done by resources on that baseline between those dates. Even manually entering baseline work for a task doesn't distribute the work hours across the baseline duration.
If you have the initial project, you can compare the fields you want from that project with those of the current project using the option: Report > Project > Compare Projects.
I hope this helps.
Ignacio