Forum Discussion
Baseline for P4W
- Jan 03, 2023
Hello daibt ,
There isn't a baseline feature out of the box for P4W currently but you could build a snapshot process yourself. An example can be seen below that a I wrote a few years ago:
https://pwmather.wordpress.com/2020/03/12/extending-projectfortheweb-part7-ppm-cds-msdyn365-powerplatform-msproject-powerapps-powerautomate-poweraddicts/ & https://pwmather.wordpress.com/2020/03/23/extending-projectfortheweb-part8-ppm-cds-msdyn365-powerplatform-msproject-powerapps-powerautomate-poweraddicts/
There are a few ways in which you could build a similar process in the Power Platform.
Paul
Hello daibt ,
There isn't a baseline feature out of the box for P4W currently but you could build a snapshot process yourself. An example can be seen below that a I wrote a few years ago:
https://pwmather.wordpress.com/2020/03/12/extending-projectfortheweb-part7-ppm-cds-msdyn365-powerplatform-msproject-powerapps-powerautomate-poweraddicts/ & https://pwmather.wordpress.com/2020/03/23/extending-projectfortheweb-part8-ppm-cds-msdyn365-powerplatform-msproject-powerapps-powerautomate-poweraddicts/
There are a few ways in which you could build a similar process in the Power Platform.
Paul
Thanks for your reply
The post helps us to take snapshot of a project
My Solutions:
- We can do take snapshot as same as the post in blog
- Synch this snapshot into Project Online, and update into one of baseline (we have 10 baseline) (we can do by Power App)
- Users (normally, they are project controler or project manager) can do baselinse analytics in Project Online
I will ask my technicians try do do in step 2, make sure that we can synch the snapshot into a baseline. How do you think about my solutions?