Forum Discussion
Knowledgeseeker
Aug 29, 2025Brass Contributor
Baseline fallback formula fails in project center
Hi Community, I have multiple projects: some have only a single baseline, some have two (Baseline and Baseline 1), and others have none. Later, I created a new project‑level, date‑type custom field...
John-project
Sep 02, 2025Silver Contributor
Knowledgeseeker,
Based on the input from my colleague Dale, you might try this alternate "old school" approach I have used for many years.
Date1=IIf([Baseline1 Start]>50000,[Baseline Start],[Baseline1 Start])
John
Knowledgeseeker
Sep 02, 2025Brass Contributor
Hi John-project
To my knowledge, this solution would only be visible locally in my Project Professional, and would not appear online for all project managers, Please correct me if I’m mistaken.
- John-projectSep 02, 2025Silver Contributor
Knowledgeseeker,
Again, I don't know because I don't use Project Online. Perhaps Dale can comment.
John