Baseline fallback formula fails in project center
Hi Community, I have multiple projects: some have only a single baseline, some have two (Baseline and Baseline 1), and others have none. Later, I created a new project‑level, date‑type custom field...
Knowledgeseeker
Sep 01, 2025Brass Contributor
Thank you for taking the time to reply to me. My formula is in French, so the one I shared was actually a translation of the French field names.
Even after changing the fields as you suggested, nothing appears.
What I find most strange is that even when I keep only [Baseline Start] in the formula, nothing is displayed.
John-project
Sep 01, 2025Silver Contributor
Knowledgeseeker,
Let's see your formula in French, maybe I can pick up something.
What exactly do you mean about keeping only Baseline Start? When you say nothing is displayed are you talking about In Project Center or Project desktop?
I'd like to see a screen shot of a typical task line with Baseline Start and Baseline1 Start and the Date field you customized with the formula.
John