Bar Styles with Rolled Up Tasks

I would like to create a bar style to format rolled up tasks. I want three different styles. I want a style to be used when a task is Rolled Up and when Flag 1 is active, a different style to be used...
  • John-project's avatar
    John-project
    Aug 28, 2023

    Thetravis12 

    Thanks for the file. I didn't know you could attach a zipped file. Previously if needed to see someone's file I'd ask them to send me their file via e-mail. So, I learned something new.

     

    This issue is that none of the subtasks under the summary lines have any Flag fields set. Just setting the Rollup field to "yes" at summary level does NOT create the display you want. There has to be something to "roll up". I showed that in my first response but I guess I didn't highlight it.

     

    I tweaked your file so it's something easier to see. I eliminated the summary level "blue house" bar style so it doesn't get in the way and then set the Flag fields. I had to toggle the "Rollup" field at each summary level from "yes" to "no" and then back to "yes" to get things "re-ordered" (I suspect your poor file is so confused that it needed a little reset). Anyway, this is what you'll have. I think it is what you want.

    If that is not what you want you'll have to give me a better explanation. I know it's all real clear in you head as to what you want but I'm not in your head.

     

    John