Automatically adjust the start and finish dates for new projects
Hello Everyone, I have old MS Project 2010 template which I use to create new project. It contains dates back in 2012. How can I adjust start and finish dates to current 2021 without breaking co...
- Aug 31, 2021Hi John,
This issue has been resolved after changing template task schedule mode from manual to auto. Some of the tasks were scheduled in manual mode.
Thanks & Regards,
Rohan
John-project
Aug 27, 2021Silver Contributor
rohanw24,
Sorry I can't help you with Project Online, ReST API or C#, I only work with the Project desktop app. Hopefully someone else with will jump in with a suggestion.
John
Sorry I can't help you with Project Online, ReST API or C#, I only work with the Project desktop app. Hopefully someone else with will jump in with a suggestion.
John
rohanw24
Aug 31, 2021Brass Contributor
Hi John,
This issue has been resolved after changing template task schedule mode from manual to auto. Some of the tasks were scheduled in manual mode.
Thanks & Regards,
Rohan
This issue has been resolved after changing template task schedule mode from manual to auto. Some of the tasks were scheduled in manual mode.
Thanks & Regards,
Rohan
- John-projectSep 01, 2021Silver Contributor