Forum Discussion
rohanw24
Aug 27, 2021Brass Contributor
Automatically adjust the start and finish dates for new projects
Hello Everyone, I have old MS Project 2010 template which I use to create new project. It contains dates back in 2012. How can I adjust start and finish dates to current 2021 without breaking co...
- Aug 31, 2021Hi John,
This issue has been resolved after changing template task schedule mode from manual to auto. Some of the tasks were scheduled in manual mode.
Thanks & Regards,
Rohan
rohanw24
Aug 27, 2021Brass Contributor
Hi John,
Thanks for the reply. Is there any automated solution or trick to do this? Actually I'm creating this project through C# into the Project Online using ReST API. So while creating a project I send EnterpriseProjectTypeId. Using this ID it automatically creates a task schedule structure for that project but with 2012 Start and Finish dates. I want it to be scheduled with 2021 dates without using Project desktop client app as it's bit time consuming process due to large no. of tasks.
Best Regards,
Rohan
Thanks for the reply. Is there any automated solution or trick to do this? Actually I'm creating this project through C# into the Project Online using ReST API. So while creating a project I send EnterpriseProjectTypeId. Using this ID it automatically creates a task schedule structure for that project but with 2012 Start and Finish dates. I want it to be scheduled with 2021 dates without using Project desktop client app as it's bit time consuming process due to large no. of tasks.
Best Regards,
Rohan
John-project
Aug 27, 2021Silver Contributor
rohanw24,
Sorry I can't help you with Project Online, ReST API or C#, I only work with the Project desktop app. Hopefully someone else with will jump in with a suggestion.
John
Sorry I can't help you with Project Online, ReST API or C#, I only work with the Project desktop app. Hopefully someone else with will jump in with a suggestion.
John
- rohanw24Aug 31, 2021Brass ContributorHi John,
This issue has been resolved after changing template task schedule mode from manual to auto. Some of the tasks were scheduled in manual mode.
Thanks & Regards,
Rohan- John-projectSep 01, 2021Silver Contributor