Automatically adjust the start and finish dates for new projects

Hello Everyone,   I have old MS Project 2010 template which I use to create new project. It contains dates back in 2012. How can I adjust start and finish dates to current 2021 without breaking co...
  • rohanw24's avatar
    rohanw24
    Aug 31, 2021
    Hi John,

    This issue has been resolved after changing template task schedule mode from manual to auto. Some of the tasks were scheduled in manual mode.

    Thanks & Regards,
    Rohan