Forum Discussion
rohanw24
Aug 27, 2021Brass Contributor
Automatically adjust the start and finish dates for new projects
Hello Everyone, I have old MS Project 2010 template which I use to create new project. It contains dates back in 2012. How can I adjust start and finish dates to current 2021 without breaking co...
- Aug 31, 2021Hi John,
This issue has been resolved after changing template task schedule mode from manual to auto. Some of the tasks were scheduled in manual mode.
Thanks & Regards,
Rohan
John-project
Aug 27, 2021Silver Contributor
rohanw24,
Use the Move Project feature found under, Project > Schedule group > Move Project.
John
Use the Move Project feature found under, Project > Schedule group > Move Project.
John
- rohanw24Aug 27, 2021Brass ContributorHi John,
Thanks for the reply. Is there any automated solution or trick to do this? Actually I'm creating this project through C# into the Project Online using ReST API. So while creating a project I send EnterpriseProjectTypeId. Using this ID it automatically creates a task schedule structure for that project but with 2012 Start and Finish dates. I want it to be scheduled with 2021 dates without using Project desktop client app as it's bit time consuming process due to large no. of tasks.
Best Regards,
Rohan- John-projectAug 27, 2021Silver Contributorrohanw24,
Sorry I can't help you with Project Online, ReST API or C#, I only work with the Project desktop app. Hopefully someone else with will jump in with a suggestion.
John- rohanw24Aug 31, 2021Brass ContributorHi John,
This issue has been resolved after changing template task schedule mode from manual to auto. Some of the tasks were scheduled in manual mode.
Thanks & Regards,
Rohan