Automatically adjust the start and finish dates for new projects
Hello Everyone, I have old MS Project 2010 template which I use to create new project. It contains dates back in 2012. How can I adjust start and finish dates to current 2021 without breaking co...
- Aug 31, 2021Hi John,
This issue has been resolved after changing template task schedule mode from manual to auto. Some of the tasks were scheduled in manual mode.
Thanks & Regards,
Rohan
John-project
Aug 27, 2021Silver Contributor
rohanw24,
Use the Move Project feature found under, Project > Schedule group > Move Project.
John
Use the Move Project feature found under, Project > Schedule group > Move Project.
John