Forum Discussion

FernandoFalchiane's avatar
FernandoFalchiane
Copper Contributor
Feb 06, 2024
Solved

Automatic task escheduling without restrictions?

Hello I have a certain problem in my schedule, where I have already carried out the planning, created the baseline and am in the control stage. There have been several delays, the project I am worki...
  • John-project's avatar
    John-project
    Feb 06, 2024
    FernandoFalchiane,
    I'm afraid you have a misunderstanding of what a baseline is. A baseline is set to capture the original plan in a group of baseline fields (i.e. Baseline Start, Baseline Duration, Baseline Cost, etc.). Those baseline fields can then be used to compare the current schedule fields with the original plan. Normally a baseline is set at the beginning of a plan before execution starts and is not changed unless there is a change in scope (e.g. tasks added/deleted). Under certain circumstances, it may be desirable set one or more new baselines if the current plan has changed considerably from the original plan.

    The "estimated" dates you refer to is what makes up the current schedule. The current schedule is dynamic. As the plan is executed task dates and durations will change in response to reality (i.e. tasks get delayed, tasks finish early, the sequence of tasks may change, etc.). Actual dates are entered via the Actual Start and Actual Finish fields if tasks do not start or finish on their scheduled dates.

    The current schedule dates and actual dates have nothing to do with baseline dates. The current schedule dates for tasks that have not started, and actual dates for tasks that have started and/or completed represent the current plan. The baseline represents the original plan.

    You "control" your schedule by tracking progress (e.g. actual work, remaining work) and adjusting the plan (i.e. revised estimates of work, adding/removing resources, changing the logic sequence of tasks, etc.). That's called managing the project.

    Hopefully this clarifies more about how Project works.

    John

Resources