automatic determination of the duration of a task
Dear Community, I can't find a solution for these two challenges in MS Project, even if I know to had already solved it once... I'd like to link tasks with each other multiple times, so that the du...
- May 28, 2025
Merlin2000,
On a quick read it sounds like you are trying to do a hammock task, particularly since you said you "solved it once". See this link for a detailed explanation on how to set it up.
https://web.archive.org/web/20200723171939/https://social.technet.microsoft.com/wiki/contents/articles/32040.ms-project-hammock-tasks.aspx
John