automatic determination of the duration of a task
- May 28, 2025
Merlin2000,
On a quick read it sounds like you are trying to do a hammock task, particularly since you said you "solved it once". See this link for a detailed explanation on how to set it up.
https://web.archive.org/web/20200723171939/https://social.technet.microsoft.com/wiki/contents/articles/32040.ms-project-hammock-tasks.aspx
John
Hi Dirk
You can try the following:
Break Task C into two milestones, Start and Finish, and link them as shown in the image.
If you want to display Summary Task C as a normal task: hide the subtasks, remove the bold from its text row, and change the Gantt bar style by double-clicking on it and applying the formatting in the attached image.
I hope this helps.
Ignacio
- John-projectMay 28, 2025Silver Contributor
Ignacio,
That's an interesting approach to emulating a hammock task. A little "back door" but it has the advantage of avoiding paste links.
John
- Ignacio_MartinMay 28, 2025Steel Contributor
Hi John
For some time now, special pastes with links (dynamic links) have been taking a long time to update (several seconds), so I try to avoid it.
Regards
Ignacio