Automatic Checkpoints
I'm trying to combine a variety of (somewhat inefficient) scheduling systems into a Project File. There are certain structures that tend to happen within a larger "broad" time definition. For examp...
Gordon_Smith
Sep 21, 2022Tin Contributor
Right now that "220" is somewhere in between. It's a magic number based on historical projects of similar complexity. What I'm fighting is a top-down "we've always done it that way" sort of thing where numbers just "get popped in" using a spreadsheet (the thumping you hear is my head on the desk). Completely separately, a MSProject file is created using the client's desired schedule for the project (more, and louder, thumping) with no regard/correlation to the estimated hours provided in the spreadsheet. That schedule is largely not worth anything, except when the client wants to use it to beat us over the head. After all, we did submit the schedule....
Right now, I'm trying to link the two in a better manner that actually treats time as something that relates to schedule, while also making the point that scheduling needs to be driven from the bottom up. So my hope was to set up a "semi-automatic" approach to creating things so that the traditional overall estimate could simply be entered, and all the subtasks autofill (again, based on past experiences). If I can get them thinking about the details without huge exertion, I'm hoping the needle can begin to shift on expectations.
Right now, I'm trying to link the two in a better manner that actually treats time as something that relates to schedule, while also making the point that scheduling needs to be driven from the bottom up. So my hope was to set up a "semi-automatic" approach to creating things so that the traditional overall estimate could simply be entered, and all the subtasks autofill (again, based on past experiences). If I can get them thinking about the details without huge exertion, I'm hoping the needle can begin to shift on expectations.
John-project
Sep 21, 2022Silver Contributor
Gordon_Smith,
I feel for you and you might want to take a couple of Excedrin for that head.
Perhaps one way to fight the "but we've always done it that way" and the client's "desired schedule" is with a counter-point approach which is a bottom up, based on detail or WBS level actuals from historical projects. If you have those actuals creating a good (realistic) plan shouldn't take that much effort. What you don't want to do is to sign on to a plan that's based solely on desires. Everybody loses.
And again, I'll re-iterate, there is no automated process in Project for creating a plan, given a framework or not.
John