Automatic Checkpoints
I'm trying to combine a variety of (somewhat inefficient) scheduling systems into a Project File. There are certain structures that tend to happen within a larger "broad" time definition. For examp...
Sep 21, 2022
Gordon --
I would opt for the first approach, but to include a summary task that includes the R&D, Design and CAD, and Documentation phases as subtasks (each of them might actually be a summary task with multiple detailed subtasks indented below them). Assuming you status your project by entering a % Complete value for each task, the overall summary task I just described would show the cumulative % Complete value for each of the subtasks (the phases). Just a thought. Perhaps others in this group will have an idea or two for you as well. Hope this helps.
I would opt for the first approach, but to include a summary task that includes the R&D, Design and CAD, and Documentation phases as subtasks (each of them might actually be a summary task with multiple detailed subtasks indented below them). Assuming you status your project by entering a % Complete value for each task, the overall summary task I just described would show the cumulative % Complete value for each of the subtasks (the phases). Just a thought. Perhaps others in this group will have an idea or two for you as well. Hope this helps.
Gordon_Smith
Sep 21, 2022Copper Contributor
But the hope would be that Project could autopopulate some of this. Can I set up a mechanism that would take the 220hrs, and a predefined relationship of 20%/60%/20% to define the durations of the subtasks?