Forum Discussion

APS1979's avatar
APS1979
Copper Contributor
Sep 15, 2021
Solved

Automated Issue of SSRS Report to Users from Project Server

We have an SSRS Highlight Report (HLR) that sits outside of Project Server, but is populated with information from project plan, custom field, risks, issues etc. 

Is it possible to automate the issuing of a project's HLR in pdf format, to a set list of recipients?

The names of recipients would be taken from the Project Site's 'Key Contacts' list (although am open to suggestions of an alternate AD field list).

 

Vague request I know, just looking into it even being a possibility before spending time detailing requirements.  Thanks in advance,.