Forum Discussion
Automate bars based on task name?
You're halfway there. All you need to do is to customize each flag field with a formula such as shown below. But be careful, testing for text strings can be tricky (i.e. misspelling, capitalization, etc.)
John
- chrisbloggs1300Jan 12, 2022Copper Contributor
John-project thank you for the informative response John, really appreciate it!
So what I've done is with the help of the lookup table function under the "text" field type is create these values based on the tasks:
It then becomes a dropdown, which based on the formula - [Text2]="*Text2 Name I created*", will autofill based on these flags which I have set up with the existing progress bars:
This works infinitely better than scrolling through 7/8 columns and lining up "yes/no" for each, but I'm still wondering if I can automate it just that little bit more...could I create an "if" statement for the "TaskName" column which looks at the actual task name field and auto-populates the "TaskName" column based on what it reads? E.g. =IF(A1=”Development”,Dev,"")...something along those lines! But then at the same time, I suppose I'm also looking at combining lookup with the formula field, which I imagine isn't possible?
Sorry for the essay! Throwing my thoughts in there wherever I can, aha!
- John-projectJan 12, 2022Silver Contributor
Ouch! Stop! You're throwing your thoughts at me too fast!
Yes you can create a custom field formula to query the text string in the Name field and dump it in abbreviated version into your Text2 field and then use that to drive your Flag fields, but why? I must be missing something.
What you cannot do is to have a single custom field that has both a lookup and a custom field formula.
If I had a clearer understanding of exactly what you are trying to do I could help more, either with custom fields or VBA, but right now, it's kinda a fog.
John
- chrisbloggs1300Jan 13, 2022Copper ContributorLet me try to give you a quick breakdown of what I'm trying to do:
Create a "Project Roadmap Schedule" is my primary task, containing all our "focus" projects for our customers (software development), which is easy enough on its own.
But, I've added another level of complexity with the addition of these custom progress bars (different colors and icons) based on each task under each project, which all follow the same task arrangement:
Development
Rack & Stack
Commissioning
UAT
Shadowing
Go Live
I'm also trying to figure out how to customize the gantt timeline itself with the program increment the project is going through / has gone through. I thought it would be as easy as right clicking the quarter or the month and hitting edit, or something along those lines, but it appears to be hiding - possibly in plain sight!